Our design office “PIRNAY plc” carries out the stability studies relating to the construction works of Lake Kivu K56 Power Plant on behalf of Global Power System ag.
The site is located approximately 10 km South of the town of Gisenyi in Rwanda, on the shore of Lake Kivu which forms the western border between Rwanda and the Congo.
The Buildings concerned by this mission are:
• Gas engine building; Steel structure and fondation
• Electrical building; Steel structure and fondation
• Foundation for transformers, ducts, trenches, tanks and black starts.
GLOBAL POWER SYSTEMS AG
GPS SWITZERLAND
3.800m²
2.350.000 €
Work in progress